things left to do
To Dos
Coding & Documentation
- km3astro [#6]
- openkm3 (@jschnabel, by week 44)
-
read from ODC -
interpret current data formats -
create lists -
add testing -
add documentation
-
- Open Data Center (ODC) @jschnabel
-
create identifiers for data sets (by week 44) -
add testing (by week 44) -
add API reference (by week 45)
-
- Open Science Platform (OSP) (by week 44) (@tgal )
-
Add quick start -
Reshuffle from Deliverable chaos -
change layout
-
- Docker
-
List in OSP
-
- VO server & VOlab (@jschnabel, by week 46)
-
documentation on setup & publishing data -
create backup solution
-
Data processing
- ANTARES sample (@jschnabel, @srgozzini , by week 43)
-
add acceptance as resource to ODC -
add background fit as resource to ODC
-
- KM3NeT data sample (by week 44)
-
create module for event selection and parameter transformation (@jschnabel) -
integrate uuid of file (@tgal) -
add quality check parameters (@rgracia) - file ID & quality parameter provided -
documenting processing chain (@jschnabel )
-
- Acoustic data [#8]
-
add metadata to /info stream -
assign static kids (by week 44)
-
- Multimessenger [#12] (by week 44)
-
Process example to include latest information (@jschnabel) -
Add Example event to OSP rather than ODC? (new page OSP)
-
Integration
- notebooks
-
add all notebooks to the /notebooks folder of OSP (by week 43) (@shallmann ) -
integrate updated openkm3 interface to notebooks (by week 44) (@jschnabel ) -
add notebook for acoustic data (by week 44) (@jschnabel)
-
- platforms
-
add related resources to Zenodo KM3NeT community (@kay.graf) - "request" on Zenodo -
upload KM3NeT example to Zenodo (by week 46) - (@jschnabel) -
integration of example notebooks to ESAP platform ( @vpestel )
-
Testing
-
Will be performed after OSP reshuffle, finalization of the notebooks (by week 46) -
test cases created "on the fly" - where to integrate the results? - next CompSoft meeting after next one?
Publication & Integration
Final deliverables
-
clarify status of review (now, add plot from data quality) -
format to official deliverable templates (by today/tomorrow)? -
circulate within working group (in week 43) -
forward to IB (Uli) (week 44)
ESCAPE
-
presentation in WP5 tech talks (Valentin, done 19th Oct, slides here) -
presentation to WP5 progress meeting (how to integrate notebooks) (week 44)
ADASS
- poster: @Google drive - (short review now, comments until 28th Oct)
- video (optional, 2do until week 44) - could integrate in OSP
- dummy proceeding (4 pages) to hand in until 1st November, possibility to adapt afterwards until beginning December
Beyond here
-
establish OSC (Open Science Committee) -
expand & integrate templates with publication procedures -
integrate sensitivity estimates -
add zooniverse data?
Edited by Feifei Huang